South-West Oxford · Project

Airport Road: Plank Line to Zenda Line

Money & projects Explore sections
South-West Oxford project

At a glance

Location
South-West Oxford
Responsible authority
South-West Oxford
Current stage
Construction ongoing at report dateAs of 2026-09-01
2026 allocation
$725,620
Next target
No next date listed

2026 road resurfacing account; part of the combined Airport Road / Mount Elgin Road contract.

Who approves and delivers this project?

Decision authority

Township Council

Approves local authorization and funding.

Money

Project money

Annual allocation

2026 allocation
$725,620
2026 named capital account in June 30 interim net budget schedule

Recorded spending

Expenditure through 2026-06-30
$10,543
CAD · Not separately stated · 2026 named capital account in June 30 interim net budget schedule

Timeline

    No dated delivery milestones are published in this record.

    Contracts

    Contract award not confirmed.

    Decisions

    No separate decision record is linked. Approval details may appear in the timeline or source documents.

    Outcomes

    Completion not confirmed.

    Questions

    Scope & interpretation notes
    • Combined contract remains on south-west-oxford-asphalt; do not duplicate full $662,834.60 award on each road. Completion narrative is dated September report, while dollars stop June 30.

    Sources & evidence

    These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

    1. TR13-2026: 2026 First and Second Quarter Budget Update

      Source ID: south-west-oxford-v7-q2

      Publisher
      Township of South West Oxford
      Published
      2026-09-01
      Event / reporting date
      2026-09-01
      Retrieved
      2026-10-01
      Verified
      2026-10-01
      Evidence status
      verified_primary
      Decision / approval status
      published
      Passage / page
      pp. 1–2 narrative; pp. 4–7 budget/actual schedule
      Evidence notes
      Actual cutoff June 30; narrative can describe later work. Capital and operating entries ongoing. Public accounting net amounts, not gross payment totals.

      Open in source library

    2. WD6-2026: asphalt tender results

      Source ID: south-west-oxford-asphalt-report

      Publisher
      Township of South West Oxford
      Published
      2026-04-07
      Event / reporting date
      2026-04-07
      Retrieved
      2026-10-01
      Verified
      2026-10-01
      Evidence status
      verified_primary
      Decision / approval status
      published
      Passage / page
      PDF pp. 1–2; bid result and scope

      Open in source library

    Make sense of the money

    Make sense of the money

    Your taxes called. They’d like a receipt.

    Budget
    Planned costs for a stated year or project.
    Annual allocation
    Funding assigned for one year. It may be part of a larger project.
    Lifetime project budget
    The stated budget for the full project across its years.
    Forecast
    An estimate of the eventual cost, as of the date shown.
    Tax requirement (levy)
    The amount to raise from property taxes, after other funding.
    Contract award
    The accepted contract price, with its stated tax and scope.
    Recorded costs or payments
    Amounts reported for the period shown. They do not establish project completion.

    County spending and County taxes explained →

    Open the full money explanation