03ProjectsSouth-West Oxford

South-West Oxford · Project

Strik Drain reconstruction

Money & projects Explore sections
South-West Oxford project

At a glance

Location
South-West Oxford
Responsible authority
South-West Oxford
Current stage
Contract award verified; final completion/payment not establishedAs of 2024-11-05
2026 allocation
Not established
Next target
No next date listed
Named supplier
TAS Excavating & Rentals Ltd. See contract details

Strik Drain reconstruction

Who approves and delivers this project?

Budget authority

Township Council

Approves annual allocation; delivery and contract authority must be traced separately.

Open the source record
  1. Official bids and tenders: published award archive Awarded tenders section: grass cutting, Piper Drain, asphalt, Strik Drain

    Township of South West Oxford

    published · Primary record verified · Primary archive opened; later closed tenders are not automatically awards.

Money

Project money

Project cost not published in this record.

Latest spending total not published here.

CAD · Source budget basis; HST treatment not separately stated · Award record; approved project budget not extracted
Open the source record
  1. Official bids and tenders: published award archive Awarded tenders section: grass cutting, Piper Drain, asphalt, Strik Drain

    Township of South West Oxford

    published · Primary record verified · Primary archive opened; later closed tenders are not automatically awards.

Timeline

    No dated delivery milestones are published in this record.

    Contracts

    2024-06 · Award approved/published

    Strik Drain reconstruction

    TAS Excavating & Rentals Ltd. · 2024-11-05

    Published bid
    Not established
    Published award / contract value
    $239,599.14
    Unit price
    Not established

    Excludes HST

    Open the source record
    1. Official bids and tenders: published award archive Awarded tenders section: grass cutting, Piper Drain, asphalt, Strik Drain

      Township of South West Oxford

      published · Primary record verified · Primary archive opened; later closed tenders are not automatically awards.

    Open procurement record

    Decisions

    No separate decision record is linked. Approval details may appear in the timeline or source documents.

    Outcomes

    Completion not confirmed.

    Questions

    • What is the latest committed cost, spending to date and completion milestone?
    Make sense of the money

    Your taxes called. They’d like a receipt.

    Budget
    Planned costs for a stated year or project.
    Annual allocation
    Funding assigned for one year. It may be part of a larger project.
    Lifetime project budget
    The stated budget for the full project across its years.
    Forecast
    An estimate of the eventual cost, as of the date shown.
    Tax requirement (levy)
    The amount to raise from property taxes, after other funding.
    Contract award
    The accepted contract price, with its stated tax and scope.
    Recorded costs or payments
    Amounts reported for the period shown. They do not establish project completion.