October 20 draft minutes record resolution 8 authorizing $1,304,091 plus applicable HST for Early Works from the Working Capital Reserve and arrangements with Sierra General Contracting, subject to approvals. A November 3 staff follow-up says Sierra was notified. Minutes adoption, an executed contract and payment are not established; this is not approval or completion of the whole facility.
South-West Oxford
Early Works authorized in draft minutes; full facility separate
Original budget
$12,000,000
Next target
2028-01-01 · Anticipated childcare occupancy in proposed MOU
Latest update
2026-11-03 · Staff report says Sierra was notified