03ProjectsOxford County

Oxford County · Project

Embro replacement fire station

Money & projects Explore sections

At a glance

Location
Zorra
Responsible authority
Zorra
Current stage
Preferred site endorsed; detailed cost and delivery plan requestedAs of 2026-08-13
2026 allocation
Not established
Next target
No next date listed

Council selected the former Public Works site at 8 Commissioners Street as the preferred location and requested separate cost, funding and implementation reports for Embro and Uniondale.

Who approves and delivers this project?

Decision authority

Township Council

Approves local authorization and funding.

Money

Project money

Project cost not published in this record.

Latest spending total not published here.

CAD · Not separately stated · See source-specific amounts

Timeline

    No dated delivery milestones are published in this record.

    Contracts

    Contract award not confirmed.

    Decisions

    Outcomes

    Completion not confirmed.

    Questions

    Sources & evidence

    These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

    1. August 13, 2026 Council minutes

      Source ID: zorra-v7-aug13-minutes

      Publisher
      Township of Zorra
      Published
      2026-08-13
      Event / reporting date
      2026-08-13
      Retrieved
      2026-10-01
      Verified
      2026-10-01
      Evidence status
      verified_primary
      Decision / approval status
      published
      Passage / page
      pp. 4–9, resolutions 07–20

      Open in source library

    Make sense of the money

    Make sense of the money

    Your taxes called. They’d like a receipt.

    Budget
    Planned costs for a stated year or project.
    Annual allocation
    Funding assigned for one year. It may be part of a larger project.
    Lifetime project budget
    The stated budget for the full project across its years.
    Forecast
    An estimate of the eventual cost, as of the date shown.
    Tax requirement (levy)
    The amount to raise from property taxes, after other funding.
    Contract award
    The accepted contract price, with its stated tax and scope.
    Recorded costs or payments
    Amounts reported for the period shown. They do not establish project completion.

    Why are there different County totals?

    The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.

    Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.

    Detailed approved budget ↗ · County budget hub ↗

    Open the full money explanation