Oxford County · Project
Airport Road and Mount Elgin Road resurfacing
Airport Road from Plank Line to Zenda Line; Mount Elgin Road from railway to Dereham Line.
Project cost not published in this record.
Latest spending total not published here.
Completion reported in September 1 report; exact physical completion date not supplied.
Sources for this record: [3]
2026-02 / resolution 7 · Award approved/published
Permanent Paving Inc. · 2026-04-07
Excludes HST
Sources for this record: [1] [2]
Open procurement record2026-04-07 · 7
Carried
$662,834.60 · Award before applicable HST
Completion not confirmed.
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Source ID: south-west-oxford-asphalt-report
Source ID: south-west-oxford-apr7-minutes
Source ID: south-west-oxford-v7-q2
Your taxes called. They’d like a receipt.
The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.
Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.
Detailed approved budget ↗ · County budget hub ↗