Budget and delivery
Town of Ingersoll — Infrastructure and Development
The service department manages delivery. Finance reports actual spending. Council approves appropriations and changes.
Sources for this record: [2]
Eight places. One shared future.
Oxford County · Project
As part of the industry-wide cellular upgrades to the Bell/Rogers networks, the existing GPS handheld controllers have become obsolete and will no longer function under the new 4 G networks by end of 2025. A new GPS Data Collector is required to continue working with the two GNSS (Global Navigation Satellite System) rover units that the Engineering Department already employs. Despite the requirement for the upgrade due to network limitations, the new GPS Data Collectors would provide significant functional improvements to their predecessors, including a larger 7-inch touch display, improved ergonomics, and runs on Windows 10 Pro, enhancing usability and productivity compared to the TSC 3's smaller screen and outdated operating system.
Budget and delivery
The service department manages delivery. Finance reports actual spending. Council approves appropriations and changes.
Sources for this record: [2]
Project money evidence: [1] [2]
$11,000Listed funding total
Start: Spring 2026; completion: Fall 2026. Budget book physical PDF page 159. These are targets, not confirmed dates.
Sources for this record: [1]
Contract award not confirmed.
No separate decision record is linked. Approval details may appear in the timeline or source documents.
Completed. Completion or reopening of this scope does not establish final acceptance, final project cost or payment.
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Source ID: ingersoll-budget-2026
Source ID: ingersoll-q2-2026
Your taxes called. They’d like a receipt.
The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.
Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.
Detailed approved budget ↗ · County budget hub ↗
Open the full money explanation