03ProjectsOxford County

Oxford County · Project

Eng - Wellington St Reconstruction ( King St to Canterbury)

Money & projects Explore sections

At a glance

Location
Ingersoll
Responsible authority
Ingersoll
Current stage
Not StartedAs of 2026-06-30
2026 allocation
$11,000
Next target
No next date listed

The project involves the replacement of cast iron watermain and sanitary sewer with new PVC piping by the County of Oxford. The Town will replace storm sewers identified by asset management in the roadway. The existing road width will remain the same but new curb and gutters will be placed. New sidewalk will replace the below standard walks currently on the right of way. This is a joint project with the County. Length of project is 280 l.m.

Who approves and delivers this project?

Budget and delivery

Town of Ingersoll — Infrastructure and Development

The service department manages delivery. Finance reports actual spending. Council approves appropriations and changes.

Open the source record
  1. T-022-26 — Q 2 operating and capital variance report Capital status pages 3–7; operating summaries pages 10–11; all 41 detailed department/facility tables pages 12–52.

    Town of Ingersoll · Published 2026-08-10 · Event/reporting date 2026-08-10 · sixmonthsended 2026-06-30

    Received as information; annualbudgetcolumn asreported June 30 · Primary record verified

Money

Project money

Annual allocation

2026 allocation
$11,000
2026 capital allocation

Latest spending total not published here.

CAD · Not separately specified in capital schedule · 2026 capital allocation
Sources for these figures · 2
  1. 2026–2027 Mayor’s Budget179 pages; original operating summary on physical page 18; capital funding on page 130; project sheets pages 131–179.
  2. T-022-26 — Q 2 operating and capital variance reportCapital status pages 3–7; operating summaries pages 10–11; all 41 detailed department/facility tables pages 12–52.
2 source records
  1. 2026–2027 Mayor’s Budget 179 pages; original operating summary on physical page 18; capital funding on page 130; project sheets pages 131–179.

    Town of Ingersoll · Published 2026-01-12 · Event/reporting date 2026-01-12 · 2026–2027

    Mayor’sbudget; Councilshortenedamendmentperiod Jan 12; originalversionpreserved · Primary record verified

  2. T-022-26 — Q 2 operating and capital variance report Capital status pages 3–7; operating summaries pages 10–11; all 41 detailed department/facility tables pages 12–52.

    Town of Ingersoll · Published 2026-08-10 · Event/reporting date 2026-08-10 · sixmonthsended 2026-06-30

    Received as information; annualbudgetcolumn asreported June 30 · Primary record verified

Where the funding comes from

$11,000Listed funding total

  1. ReservesOriginal January 2026 capital funding schedule, physical PDFp 130; funding may be later amended.
    $11,000100% of listed total
Listed funding adds to the 2026 allocation amount. CAD.
Sources for these figures · 2
  1. 2026–2027 Mayor’s Budget179 pages; original operating summary on physical page 18; capital funding on page 130; project sheets pages 131–179.
  2. T-022-26 — Q 2 operating and capital variance reportCapital status pages 3–7; operating summaries pages 10–11; all 41 detailed department/facility tables pages 12–52.

Timeline

  1. original target

    Original project-sheet schedule

    Start: Summer 2026; completion: Fall 2028. Budget book physical PDF page 149. These are targets, not confirmed dates.

    Open the source record
    1. 2026–2027 Mayor’s Budget 179 pages; original operating summary on physical page 18; capital funding on page 130; project sheets pages 131–179.

      Town of Ingersoll · Published 2026-01-12 · Event/reporting date 2026-01-12 · 2026–2027

      Mayor’sbudget; Councilshortenedamendmentperiod Jan 12; originalversionpreserved · Primary record verified

Contracts

Contract award not confirmed.

Decisions

No separate decision record is linked. Approval details may appear in the timeline or source documents.

Outcomes

Completion not confirmed.

Questions

  • What is the current forecast cost and expected completion date?
Scope & interpretation notes
  • Annual allocation and YTD expense, not lifetime project cost. T-022-26 PDFp 5.
Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

Why are there different County totals?

The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.

The budget hub retains an earlier $406.1 million headline. Spending explanations here use the detailed approved schedule.

Detailed approved budget ↗ · County budget hub ↗

Open the full money explanation