03ProjectsOxford County

Oxford County · Project

Township Road 6B hard surface

Money & projects Explore sections

At a glance

Location
Blandford-Blenheim
Responsible authority
Blandford-Blenheim
Current stage
2025 costs reported; delivery separately verifiedAs of 2026-10-01
2026 allocation
Not established
Next target
No next date listed

Township Road 6B hard surface

Who approves and delivers this project?

Municipal authority

Township of Blandford-Blenheim

Budget and municipal project owner; contractor/individual decisions require separate records.

Open the source record
  1. 2025 development charges annual report PDF pp.1–2 narrative, p.4 reserve movement, p.5 project costs and funding

    Township of Blandford-Blenheim · Published 2026-03-25 · Event/reporting date 2026-03-25

    · Primary record verified · For April 1 Council. Narrative opening DC balance $205,763.27 conflicts with table $205,763.67 by $0.40; table balance reconciles. Header report number Financial Services 2026-03 while recommendation TR-26-05. Project figures are 2025 costs, not lifetime final totals.

Money

Project money

Recorded spending

Expenditure through 2025-12-31
$251,302.43
CAD · See individual funding/contract source · 2025 incurred costs only; lifetime original/revised budget not established
Open the source record
  1. 2025 development charges annual report PDF pp.1–2 narrative, p.4 reserve movement, p.5 project costs and funding

    Township of Blandford-Blenheim · Published 2026-03-25 · Event/reporting date 2026-03-25

    · Primary record verified · For April 1 Council. Narrative opening DC balance $205,763.27 conflicts with table $205,763.67 by $0.40; table balance reconciles. Header report number Financial Services 2026-03 while recommendation TR-26-05. Project figures are 2025 costs, not lifetime final totals.

Where the funding comes from

$251,302.43Listed funding total

  1. Development charges2025 cost funding; not full lifetime funding
    $26,43710.5% of listed total
  2. Reserves2025 cost funding; not full lifetime funding
    $224,865.4389.5% of listed total
This is the total of the listed financing amounts. It is not a confirmed whole-project funding total. CAD.

Timeline

    No dated delivery milestones are published in this record.

    Contracts

    Contract award not confirmed.

    Decisions

    No separate decision record is linked. Approval details may appear in the timeline or source documents.

    Outcomes

    Completion not confirmed.

    Questions

    • What is the latest approved forecast and cost incurred on this project?
    Make sense of the money

    Your taxes called. They’d like a receipt.

    Budget
    Planned costs for a stated year or project.
    Annual allocation
    Funding assigned for one year. It may be part of a larger project.
    Lifetime project budget
    The stated budget for the full project across its years.
    Forecast
    An estimate of the eventual cost, as of the date shown.
    Tax requirement (levy)
    The amount to raise from property taxes, after other funding.
    Contract award
    The accepted contract price, with its stated tax and scope.
    Recorded costs or payments
    Amounts reported for the period shown. They do not establish project completion.

    Why are there different County totals?

    The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.

    The budget hub retains an earlier $406.1 million headline. Spending explanations here use the detailed approved schedule.

    Detailed approved budget ↗ · County budget hub ↗

    Open the full money explanation