Princeton municipal drain and street upgrades

Money & projects Explore sections

At a glance

Location
Blandford-Blenheim
Responsible authority
Blandford-Blenheim
Current stage
2025 costs reported; delivery separately verifiedAs of 2026-10-01
2026 allocation
Not established
Next target
No next date listed

Princeton municipal drain and street upgrades

Who approves and delivers this project?

Municipal authority

Township of Blandford-Blenheim

Budget and municipal project owner; contractor/individual decisions require separate records.

Money

Project money

Recorded spending

Expenditure through 2025-12-31
$5,164,658.72
CAD · See individual funding/contract source · 2025 incurred costs only; lifetime original/revised budget not established

Where the funding comes from

$5,164,658.72Listed funding total

  1. Debt2025 cost funding; not full lifetime funding
    $1,000,00019.4% of listed total
  2. Canada Community-Building Fund2025 cost funding; not full lifetime funding
    $1,000,00019.4% of listed total
  3. Development charges2025 cost funding; not full lifetime funding
    $50,0001% of listed total
  4. Other2025 cost funding; not full lifetime funding
    $271,9585.3% of listed total
  5. Oxford County2025 cost funding; not full lifetime funding
    $2,224,938.3343.1% of listed total
  6. Reserves2025 cost funding; not full lifetime funding
    $617,762.3912% of listed total
This is the total of the listed financing amounts. It is not a confirmed whole-project funding total. CAD.

Timeline

    No dated delivery milestones are published in this record.

    Contracts

    2025-02 · Closed; award not extracted

    Princeton drainage Phase 4

    Awardee not established

    Published bid
    Not established
    Published award / contract value
    Not established
    Unit price
    Not established

    Not stated in opened record

    Closing date 2025-02-20. Award amount remains null without primary award value.

    Open procurement record

    2024-01 · Awarded; vendor/value not displayed

    Princeton drainage Phase 3

    Awardee not established · 2024-03-06

    Published bid
    Not established
    Published award / contract value
    Not established
    Unit price
    Not established

    Not stated in opened record

    Closing date None. Award amount remains null without primary award value.

    Open procurement record

    Decisions

    No separate decision record is linked. Approval details may appear in the timeline or source documents.

    Outcomes

    Completion not confirmed.

    Questions

    • What is the latest approved forecast and cost incurred on this project?

    Related issues

    Will the Township publish a street-by-street finish date, access notice and final inspection result for Princeton Phase 5?

    Sources & evidence

    These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

    1. 2025 development charges annual report

      Source ID: blandford-blenheim-dc-report-2025

      Publisher
      Township of Blandford-Blenheim
      Published
      2026-03-25
      Event / reporting date
      2026-03-25
      Retrieved
      2026-10-01
      Verified
      2026-10-01
      Evidence status
      verified_primary
      Passage / page
      PDF pp.1–2 narrative, p.4 reserve movement, p.5 project costs and funding
      Evidence notes
      For April 1 Council. Narrative opening DC balance $205,763.27 conflicts with table $205,763.67 by $0.40; table balance reconciles. Header report number Financial Services 2026-03 while recommendation TR-26-05. Project figures are 2025 costs, not lifetime final totals.

      Open in source library

    2. Princeton drainage Phase 4 procurement

      Source ID: blandford-blenheim-tender-phase4

      Publisher
      Township of Blandford-Blenheim
      Retrieved
      2026-10-01
      Verified
      2026-10-01
      Evidence status
      verified_primary
      Passage / page
      Public tender summary and award status
      Evidence notes
      Opened full primary portal. Plan takers and unofficial bidders are not recorded as awarded suppliers.

      Open in source library

    3. Princeton drainage Phase 3 procurement

      Source ID: blandford-blenheim-tender-phase3

      Publisher
      Township of Blandford-Blenheim
      Retrieved
      2026-10-01
      Verified
      2026-10-01
      Evidence status
      verified_primary
      Passage / page
      Public tender summary and award status
      Evidence notes
      Opened full primary portal. Plan takers and unofficial bidders are not recorded as awarded suppliers.

      Open in source library

    Make sense of the money

    Make sense of the money

    Your taxes called. They’d like a receipt.

    Budget
    Planned costs for a stated year or project.
    Annual allocation
    Funding assigned for one year. It may be part of a larger project.
    Lifetime project budget
    The stated budget for the full project across its years.
    Forecast
    An estimate of the eventual cost, as of the date shown.
    Tax requirement (levy)
    The amount to raise from property taxes, after other funding.
    Contract award
    The accepted contract price, with its stated tax and scope.
    Recorded costs or payments
    Amounts reported for the period shown. They do not establish project completion.

    Why are there different County totals?

    The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.

    Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.

    Detailed approved budget ↗ · County budget hub ↗

    Open the full money explanation