Cowan Sportsplex Indoor Synthetic Turf Replacement

11353

Money & projects Explore sections
Woodstock procurementAwarded

Supplier

WorldWide Turf Inc.

Procurement method
Public tender
Award date
2026-05-26
Contract term
Not established

From bid to payment

Awarded

  1. Published bidAmount not published
  2. RecommendationAmount not published
  3. Award / contractAmount not publishedWorldWide Turf Inc. · 2026-05-26
  4. Recorded paymentsAmount not publishedNo payment amounts attached
Not published in award value field · Bid, award and payment are separate measures.

Primary award notice verifies supplier and date where displayed. Dollar value not disclosed in the awarded-vendor field. A closed tender without an award notice does not establish its winner.

Open the source record
  1. Cowan Sportsplex Indoor Synthetic Turf Replacement Public bid overview, Awarded vendor list and unofficial results

    City of Woodstock · Published 2026-05-26 · Event/reporting date 2026-05-26 · 2026

    Published primary record · Primary record verified · Downloaded full public HTML. Award value column is blank; winning bid results are not substituted for contract value.

Contract changes & payments

Contract changes unconfirmed.

Payments not confirmed.

The project this pays for

Woodstock · Other projects

Indoor Turf Replacement

New indoor turf is installed. The City announced the turf and walking track would reopen September 14.

Woodstock

Installation complete; reopening announced
2026 allocation
$950,000
Named supplier
WorldWide Turf Inc.
Next target
No next date listed
Latest update
2026-09-11 · Turf installation complete

What still needs an answer

  • What is the signed contract value, approved change orders and cumulative amount paid?
Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

Why are there different County totals?

The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.

The budget hub retains an earlier $406.1 million headline. Spending explanations here use the detailed approved schedule.

Detailed approved budget ↗ · County budget hub ↗