02Follow the moneyOxford County

Oxford County · Procurement record

Nesbitt Crescent & Vanier Avenue Reconstruction

ENG2026-11441 & 11445

Money & projects Explore sections
Woodstock procurementClosed

Supplier

Not established in the reviewed record

Procurement method
Public tender
Award date
Not established
Contract term
Not established

From bid to payment

Closed

  1. Published bidAmount not published
  2. RecommendationAmount not published
  3. Award / contractAmount not published
  4. Recorded paymentsAmount not publishedNo payment amounts attached
Not published in award value field · Bid, award and payment are separate measures.

Primary award notice verifies supplier and date where displayed. Dollar value not disclosed in the awarded-vendor field. A closed tender without an award notice does not establish its winner.

Open the source record
  1. Nesbitt Crescent & Vanier Avenue Reconstruction Public bid overview, Awarded vendor list and unofficial results

    City of Woodstock · 2026

    Published primary record · Primary record verified · Downloaded full public HTML. Award value column is blank; winning bid results are not substituted for contract value.

Contract changes & payments

Contract changes unconfirmed.

Payments not confirmed.

The project this pays for

Woodstock · Roads & bridges

Nesbitt Cr Recon - Nellis to Nellis

Nesbitt Cr Recon - Nellis to Nellis

Woodstock

Tender closed · award unconfirmed
2026 allocation
$1,424,000
Next target
No next date listed
Latest update
2025-12-11 · 2026 capital allocation adopted

Woodstock · Roads & bridges

Vanier Rd Recon - Nesbitt to Nesbitt

Vanier Rd Recon - Nesbitt to Nesbitt

Woodstock

Tender closed · award unconfirmed
2026 allocation
$520,000
Next target
No next date listed
Latest update
2025-12-11 · 2026 capital allocation adopted

What still needs an answer

  • What is the signed contract value, approved change orders and cumulative amount paid?
Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

Why are there different County totals?

The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.

The budget hub retains an earlier $406.1 million headline. Spending explanations here use the detailed approved schedule.

Detailed approved budget ↗ · County budget hub ↗

Open the full money explanation