02Follow the moneyOxford County

Oxford County · Procurement record

Stoney Creek sanitary sewer erosion repair

RFT2025-007

Money & projects Explore sections
Tillsonburg procurementAwarded

Supplier

J-AAR Civil Infrastructures Limited

Procurement method
RFT
Award date
2026-01-12
Contract term
Not established

From bid to payment

Awarded

  1. Published bidAmount not published
  2. RecommendationAmount not published
  3. Award / contractAmount not publishedJ-AAR Civil Infrastructures Limited · 2026-01-12
  4. Recorded paymentsAmount not publishedNo payment amounts attached
Not stated in opened record · Bid, award and payment are separate measures.

Award summary explicitly identifies J-AAR. Ownership/funding of sanitary asset not inferred from procurement authority.

Open the source record
  1. Stoney Creek sanitary sewer erosion repair procurement record Bid summary, status, award summary and public results

    Town of Tillsonburg

    · Primary record verified · Award summary explicitly identifies J-AAR. Ownership/funding of sanitary asset not inferred from procurement authority.

Contract changes & payments

Contract changes unconfirmed.

Payments not confirmed.

The project this pays for

Tillsonburg · Water, drainage & wastewater

Stoney Creek sanitary sewer erosion repair

Stoney Creek sanitary sewer erosion repair

Tillsonburg

Awarded
2026 allocation
Not established
Named supplier
J-AAR Civil Infrastructures Limited
Next target
No next date listed
Latest update
2026-01-12 · Stoney Creek sanitary sewer erosion repair award

What still needs an answer

Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

Why are there different County totals?

The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.

The budget hub retains an earlier $406.1 million headline. Spending explanations here use the detailed approved schedule.

Detailed approved budget ↗ · County budget hub ↗

Open the full money explanation