Award / contract$373,454.20Vandenberk Construction · 2026-10-21
Recorded paymentsAmount not publishedNo payment amounts attached
Accepted bid exclusive of taxes; $50,000 contingency specified separately in staff report, if needed. An executed contract and payment are not established. · Bid, award and payment are separate measures. No price-change calculation is inferred between them.
Posted October 21 written minutes record a carried motion accepting Vandenberk Construction Inc.’s bid of $373,454.20 exclusive of taxes, with contingency if needed, and authorizing the CAO and Treasurer to sign. The staff report specifies $50,000 contingency; the motion does not repeat that amount. Formal minutes adoption, an executed agreement and completion have not been verified. The earlier caption evidence remains historical; no individual voting record or independent audio review is inferred.
Posted October 21 written minutes record a carried motion accepting Vandenberk Construction Inc.’s bid of $373,454.20 exclusive of taxes, with contingency if needed, and authorizing the CAO and Treasurer to sign. The staff report specifies $50,000 contingency; the motion does not repeat that amount. Formal minutes adoption, an executed agreement and completion have not been verified.
East Zorra-Tavistock
Bid acceptance recorded in written minutes; adoption unverified
2026 allocation
$600,000
Named supplier
Vandenberk Construction
Next target
No next date listed
Latest update
2026-10-21 · Written minutes record bid acceptance
Open project →
What still needs an answer
Where are the adopted minutes, executed replacement agreement and completion record?
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
staff-reported termination; replacement award unverified
Passage / page
Report pages 1–2
Evidence note
Primary-source body reviewed in the October 30 audit No October 21 minutes linked. Replacement award and completion unverified. Original capital budget $600,000; paid-to-date $130,486.98 reported.
39:54–40:37 of 42:02; motion called carried at 40:34/40:37
Evidence note
Only the target caption window was reviewed. Correct contractor, amount and $50,000 contingency come from written CAO2026-17 report. Audio, written minutes, individual votes, executed agreement and completion were not independently verified.
Posted written minutes record a carried motion. Formal adoption at the November 4 meeting was not verified. Signing authority is not proof of an executed agreement.
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.
Why are there different County totals?
The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.
Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.