Oxford County · Procurement record

Oxford Road 30 (11th Line) Slope Stability - Woodstock

TENDER-ENG-2026-712

Money & projects Explore sections
Oxford County procurementawardee named in annual register

Supplier

Cambridge Landscaping & Construction Ltd

Procurement method
TENDER
Award date
Not established
Contract term
Not established

From bid to payment

awardee named in annual register

  1. Published bid$580,564.06
  2. RecommendationAmount not published
  3. Award / contractAmount not publishedCambridge Landscaping & Construction Ltd
  4. Recorded paymentsAmount not publishedNo payment amounts attached
Not established in annual register · Bid, award and payment are separate measures. A bid is not the final executed contract value.

Published bid is not an executed or final contract value. The register provides no dated award or payment history.

Open the source record
  1. 2026 procurement register: Oxford Road 30 (11th Line) Slope Stability - Woodstock TENDER-ENG-2026-712

    Oxford County · 2026

    register entry · Primary record verified · Full annual register downloaded and parsed. Contract-value field is -- for this entry; this is not proof the contract does not exist.

Contract changes & payments

Contract changes unconfirmed.

Payments not confirmed.

The project this pays for

County · Roads & bridges

Oxford Road 30 slope and trail stabilization

Stabilize slope by Standard Tube, Burgess and Rotary Millennium trails on11thLine.

Woodstock

August–November 2026 construction target
2026 allocation
$100,000
Named supplier
Cambridge Landscaping & Construction Ltd
Next target
2026-11 · Expected completion
Latest update
2025-12-10 · 2026 Business Plan and Budget approval

What still needs an answer

  • What was the signed contract value and tax basis?
  • Were any changes approved, and what has been paid?
Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

Why are there different County totals?

The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.

The budget hub retains an earlier $406.1 million headline. Spending explanations here use the detailed approved schedule.

Detailed approved budget ↗ · County budget hub ↗

Open the full money explanation