Culvert replacements on parts of Oxford Roads 2, 10, 13, 22, 55 and 59, plus a left-turn lane at Oxford Road 2 and 35th Line.
Blandford-Blenheim · East Zorra-Tavistock · South-West Oxford · Zorra
Named OR2/OR22/OR59 sections complete; OR10 scheduled mid-October–end-November
2026 allocation
Not established
Named supplier
Steve Smith Construction Corporation
Next target
2026-10 · Oxford Road 10 start target
Latest update
2026-10-29 · Section-specific status reviewed
Open project →
What still needs an answer
What was the signed contract value and tax basis?
Were any changes approved, and what has been paid?
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.
Why are there different County totals?
The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.
Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.