02Follow the moneyZorra

Zorra · Procurement record

Commissioners Street crack sealing

Money & projects Explore sections
Zorra procurementAward reported

Supplier

Roadmaster Constructions and Sealing Inc.

Procurement method
County joint tender
Award date
Not established
Contract term
Not established

From bid to payment

Award reported

  1. Published bidAmount not published
  2. RecommendationAmount not published
  3. Award / contract$17,400Roadmaster Constructions and Sealing Inc.
  4. Recorded paymentsAmount not publishedNo payment amounts attached

Unit price: $3.48 linear metre

Not specified in report amount · Bid, award and payment are separate measures. A unit price is not an annual contract total.

5,000 metres planned; September completion scheduled in August report, not verified delivery.

Contract changes & payments

Contract changes unconfirmed.

Payments not confirmed.

What still needs an answer

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. Report 2026-075: Roads Division quarterly update

    Source ID: zorra-v7-q2-roads

    Publisher
    Township of Zorra
    Published
    2026-08-13
    Event / reporting date
    2026-08-13
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published
    Passage / page
    pp. 1–5
    Evidence notes
    Report includes July events despite Q2 label; tax basis is amount-specific.

    Open in source library

Make sense of the money

Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

County spending and County taxes explained →