Blandford-Blenheim · Project
The September 24 notice set a weather-dependent October 10 paving target. A November 7 source check did not establish later Phase 5 completion, inspection or current road access. June 17 adopted minutes record a $1,091,195.04 plus HST award to Armstrong Paving and Materials Group Ltd.; this is not final expenditure.
Final top asphalt on Main Street and adjoining Princeton streets; tender includes surface asphalt and a pedestrian crossing.
Project cost not published in this record.
Latest spending total not published here.
Resolution 2026-06-17-10 awards $1,091,195.04 plus HST to Armstrong Paving and Materials Group Ltd. Award is not final expenditure or proof of completed paving.
Sources for this record: [3]
The September 24 notice scheduled final asphalt through October 10, weather permitting. That target has passed; no later completion confirmation was established in the October 29 review. Retain the original schedule as history and confirm current access with the Township.
Sources for this record: [2]
CAO26-35 page 7 does not confirm Phase 5 final paving completion, inspection or current road access.
Sources for this record: [4]
2026-09 · Award recorded in adopted June 17 minutes; completion unverified
Armstrong Paving Group · 2026-06-17
Plus HST; tax amount not calculated here
Resolution 2026-06-17-10 names Armstrong Paving and Materials Group Ltd. and awards $1,091,195.04 plus HST. Earlier notices use the shorter name Armstrong Paving Group. This does not establish executed contract terms, final expenditure, completion, inspection or current access.
Sources for this record: [1] [2] [3]
Open procurement recordNo separate decision record is linked. Approval details may appear in the timeline or source documents.
No later Phase 5 completion, inspection or current access confirmation was established in the November 7 review. The November 4 term review discusses broader reconstruction, not a Phase 5 completion certificate.
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Source ID: blandford-blenheim-tender-phase5
Source ID: blandford-blenheim-phase5-notice
Source ID: nov7-bb-june17-phase5-award
Source ID: nov7-bb-cao26-35-term-review